Modularisation and coordination of plantroom into prefabricated modules
BIM Modelling and production of shop drawings, with all materials and cutting lists scheduled
Structural design and certification of the prefabricated modules
Design Achievements:
Off-site manufacturing of the plantroom enabled the mechanical construction program to be compressed by 8-12 weeks compared to traditional site construction.
Prefab modules lifted into position over a weekend, with formwork construction commencing the next day
Design Highlights:
Frames constructed using weld-free SUPA framing
Provision of material schedules allowed for accurate materials ordeing and minimised wastage
Modules weighed up to 8.5t
Design Considerations:
Lifting
Assembly
Seismic
Operating loads & vibration